| Summary of Bond Scope |
|
||||
| Overview |
|||||
| Proposal #1 Items |
In Dollars |
Percentage |
|||
| New Pattengill Middle School Including 850 seat performing arts auditorium) |
37,043,901 |
54.19661071 |
|||
| Roof, Science & Computer Lab Renovations at Otto Middle School |
2,300,834 |
3.366206076 |
|||
| Roof, Science & Computer Lab Renovations at Gardner Middle School |
1,623,813 |
2.375699067 |
|||
| Roof, Science & Computer Lab Renovations at Dwight Rich Middle School |
1,623,813 |
2.375699067 |
|||
| Renovations at Eastern High School |
6,024,800 |
8.81450742 |
|||
| Renovations at Sexton High School |
8,659,062 |
12.66853111 |
|||
| Renovations at Everett High SchooI |
8,236,063 |
12.04966778 |
|||
| Magnet Multipurpose/Cafeterium Addition |
2,838,669 |
4.153078768 |
|||
| Sub-Total |
68,350,955 |
100 |
|||
| Less Interest Earnings |
-883,404 |
||||
| Total |
67,467,551 |
||||
| Proposal #2 Items |
|||||
| New Community/Competition Swimming Pool |
$6,085,327 |
81.05736009 |
|||
| Synthetic Turf at Sexton and Everett Football Fields |
1,422,106 |
18.94263991 |
|||
| Total |
7,507,433 |
100 |
|||
| Total Bond |
75,858,388 |
||||
| Less Interest Earnings |
-883,404 |
||||
| Total |
74,974,984 |
||||
| Detail |
|||||
| Proposal #1 Items |
|||||
| New Middle School to Replace Pattengill (including 850 seat performing arts auditorium) |
|||||
| Building Construction |
22,900,500 |
||||
| Sitework, Utilities and Athletic Fields |
2,518,200 |
||||
| Furniture & Equipment |
1,402,390 |
||||
| Technology Data Cabling |
0 |
||||
| Site Acquisition Costs |
0 |
||||
| Off Site Utility Improvements |
500,000 |
||||
| Demolish Existing Pattengill |
500,000 |
||||
| Pattengill Site Restoration |
250,000 |
||||
| Sub-Total Construction Costs |
$28,071,090 |
||||
| Project Contingency at approximately 8% |
2,205,687 |
||||
| Total Construction Costs |
$30,276,777 |
||||
| A/E Design and Document Cost at approximately 7% |
2,084,374 |
||||
| Construction Management |
535,981 |
||||
| Supervision |
1,004,784 |
||||
| General Conditions and Reimburseables at approximately 3.5% |
1,042,187 |
||||
| Inflation at approximately 3.5% |
1,042,187 |
||||
| Issuance Costs |
1,057,611 |
||||
| Total Project Cost |
$37,043,901 |
54.19661071 |
|||
| Roof, Science & Computer Lab Renovations at Otto Middle School |
|||||
| Roof replacement for areas over 20 years old (64,280 sft at $8 per sft) |
$514,240 |
||||
| Renovate existing science rooms (max. of 7) |
672,000 |
||||
| Renovate existing computer labs (max. of 2) |
169,000 |
||||
| Furniture & Equipment |
306,000 |
||||
| Sub-Total Construction Costs |
$1,661,240 |
||||
| Project Contingency at approximately 8% |
132,899 |
||||
| Total Construction Costs |
$1,794,139 |
||||
| A/E Design and Document Cost at approximately 7% |
125,589 |
||||
| Construction Management |
32,294 |
||||
| Supervision |
146,965 |
||||
| General Conditions and Reimburseables at 3.5% |
62,794 |
||||
| Inflation at 3.5% |
62,794 |
||||
| Issuance Costs |
76,259 |
||||
| Total Project Cost |
$2,300,834 |
3.366206076 |
|||
| Roof, Science & Computer Lab Renovations at Gardner Middle School |
|||||
| Roof replacement at all areas over 20 years old |
$0 |
||||
| Renovate existing science rooms (max. of 7) |
672,000 |
||||
| Renovate existing computer labs (max. of 2) |
169,000 |
||||
| Equipment |
306,000 |
||||
| Sub. Total Construction Costs |
$1,147,000 |
||||
| Project Contingency at approximately 8% |
91,760 |
||||
| Total Construction Costs |
$1,238,760 |
||||
| A/E Design and Document Cost at approximately 7% |
86,713 |
||||
| Construction Management |
22,297 |
||||
| Supervision |
146,965 |
||||
| General Conditions and Reimburseables at 3.5% |
43,356 |
||||
| Inflation at 3.5% |
43,356 |
||||
| Issuance Costs |
42,366 |
||||
| Total Project Cost |
$1,623,813 |
2.375699067 |
|||
| Roof, Science & Computer Lab Renovations at Dwight Rich Middle School |
|||||
| Roof replacement at all areas over 20 years old |
$0 |
||||
| Renovate existing science rooms (max. of 7) |
672,000 |
||||
| Renovate existing computer labs (max. of 2) |
169,000 |
||||
| Equipment |
306,000 |
||||
| Sub-Total Constructon Costs |
$1,147,000 |
||||
| Project Contingenty at approximately 8% |
91,760 |
||||
| Total Construction Costs |
$1,238,760 |
||||
| A/E Design and Document Cost at approximately 7% |
86,713 |
||||
| Construction Management |
22,297 |
||||
| Supervision |
146,965 |
||||
| General Conditions and Reimburseables at 3.5% |
43,356 |
||||
| Inflation at 3.5% |
43,356 |
||||
| Issuance Costs |
42,366 |
||||
| Total Project Cost |
$1,623,813 |
2.375699067 |
|||
| Renovations at Eastern High School |
|||||
| (Eastem football field, track, field lighting and stands to be improved using BTS and Capital Projects Funds - not Bond Issue Proceeds) |
|||||
| Roof replacement at all areas over 20 years old (10,820 sft @ $8 per sft) |
$86,560 |
||||
| Renovate Esisting Science Rooms (max. of 9) |
1,080,000 |
||||
| Renovate Computer Labs (max. of 2) |
195,000 |
||||
| Furniture and Equipment |
605,600 |
||||
| Weight room and condioning room |
263,640 |
||||
| Locker rooms |
710,990 |
||||
| Renovate Media Center |
212,400 |
||||
| Renovate Gymnasium in Eastern (not the fieldhouse) |
830,160 |
||||
| Gvmnasium Bleachers |
0 |
||||
| Renovate Cafeteria Eating Area |
462,500 |
||||
| Project Contingency at approximately 8% |
355,748 |
||||
| Total Construction Costs |
$4,802,598 |
||||
| A/E Design and Document Cost at approximately 7% |
336,181 |
||||
| Construction Management |
86,446 |
||||
| Supervision |
293,930 |
||||
| General Conditions and Reimburseables at 3.5% |
168,090 |
||||
| Inflation at 3.5% |
168,090 |
||||
| Issuance Costs |
169,465 |
||||
| Total Project Cost |
$6,024,800 |
8.81450742 |
|||
|
Renovations at Sexton High School |
|||||
| Roof replacement at all areas over 20 years old (18,825 sft @ $8 per sft) |
$150,500 |
||||
| Renovate existing Science Rooms (max. of 9) |
1,080,000 |
||||
| Renovate Computer labs (max. of 2) |
195,000 |
||||
| Renovate Media Center |
225,960 |
||||
| Renovate Gymnasium |
708,780 |
||||
| Replace Gymnasium Bleachers |
100,000 |
||||
| Replace Concessions Building |
325,000 |
||||
| Renovate Weight Room and Conditioning Room |
497,185 |
||||
| Locker Rooms |
543,760 |
||||
| Running Track |
500,000 |
||||
| Replace Football Bleachers |
525,000 |
||||
| Replace Footbal Field Lighting |
140,000 |
||||
| Replace Natural Grass Turf &. Drainage |
250,000 |
||||
| Furniture and Equipment |
608,990 |
||||
| Allowance for fields, paving and fencing |
450,000 |
||||
| Renovate Cafeteria Eating Area |
191,500 |
||||
| Sub-Total Construction Costs |
$6,491,775 |
||||
| Project Contingency at approximately 8% |
519,342 |
||||
| Total Construction Costs |
$7,011,117 |
||||
| A/E Design and Document Cost at approximately 7% |
537,393 |
||||
| Construction Management |
121,340 |
||||
| Supervision |
293,930 |
||||
| General Conditions and Reimburseables at approximatey 3.5% |
235,939 |
||||
| Inflation at approximately 3.5% |
235,939 |
||||
| Issuance Costs |
223,404 |
||||
| Total Project Cost |
$8,659,062 |
10.25752603 |
|||
|
Renovations at Everett High School |
|||||
| Roof replacement at all areas over 20 years old (18,825 sft @ $8 per sft) |
$0 |
||||
| Renovate existing Science Rooms (max. of 9) |
1,080,000 |
||||
| Renovate Computer labs (max. of 2) |
195,000 |
||||
| Renovate Media Center |
275,220 |
||||
| Renovate Gymnasium |
841,500 |
||||
| Replace Gymnasium Bleachers |
249,625 |
||||
| Replace Concessions Building |
325,000 |
||||
| Athletic Site Improvements |
450,000 |
||||
| Furniture and Equipment |
621,305 |
||||
| Renovate Weight Room and Conditioning Room |
234,390 |
||||
| Renovate Locker Rooms |
509,040 |
||||
| Running Track |
600,000 |
||||
| Replace Football Bleachers |
50,000 |
||||
| Replace Footbal Field Lighting |
140,000 |
||||
| Replace Natural Grass Turf &. Drainage |
250,000 |
||||
| Renovate Cafeteria Eating Area |
355,250 |
||||
| Sub-Total Construction Costs |
6,176,330 |
||||
| Project Contingency at approximately 8% |
474,106 |
||||
| Total Construction Costs |
$6,650,436 |
||||
| A/E Design and Document Cost at approximately 7% |
482,657 |
||||
| Construction Management |
141,425 |
||||
| Supervision |
293,930 |
||||
| General Conditions and Reimburseables at approximately 3.5% |
224,015 |
||||
| Inflation at approximately 3.5% |
224,015 |
||||
| Issuance Costs |
219,585 |
||||
| Total Project Cost |
$8,236,063 |
||||
|
Magnet School Multipurpose/Cafetorium Addition |
|||||
| New Multipurpose Cafetorium (including equipment) |
$1,874,844 |
||||
| Site Development |
180,000 |
||||
| Sub-Total Construction Costs |
$2,054,844 |
||||
| Project Contingency at approximately 8% |
158,400 |
||||
| Total Construction Costs |
$2,213,244 |
||||
| A/E Design and Document Cost at approximately 7% |
149,688 |
||||
| Construction Management |
39,838 |
||||
| Supervision |
202,595 |
||||
| General Conditions and Reimburseables at approximately 3.5% |
77,463 |
||||
| Inflation at approximately 3.5% |
77,463 |
||||
| Issuance Costs |
78,378 |
||||
| Total Project Cost |
$2,838,669 |
||||
| Proposal #2 Items (Including professional fees and issuance costs) |
|||||
| New Community/Competition Swimming Pool |
$6,085,327 |
81.05736009 |
|||
| Synthetic Turf at Sexton and Everett Football Fields |
1,422,106 |
18.94263991 |
|||
| Sub-Total |
$7,507,433 |
100 |
|||
| Note: If proposal #2 passes the $250,000 turf allowance in |
|||||
| Proposal #1 at both Sexton and Everett will be used to improve |
|||||
| other athletic sites including baseball and softball fields. |
|||||
Source: Lansing School District, 2003