Summary of Bond Scope

   

           

Overview

         

Proposal #1 Items 

     

In Dollars

Percentage

New Pattengill Middle School Including 850 seat performing arts auditorium)

37,043,901

54.19661071

Roof, Science & Computer Lab Renovations at Otto Middle School

2,300,834

3.366206076

Roof, Science & Computer Lab Renovations at Gardner Middle School

1,623,813

2.375699067

Roof, Science & Computer Lab Renovations at Dwight Rich Middle School

1,623,813

2.375699067

Renovations at Eastern High School

 

6,024,800

8.81450742

Renovations at Sexton High School

 

8,659,062

12.66853111

Renovations at Everett High SchooI

 

8,236,063

12.04966778

Magnet Multipurpose/Cafeterium Addition

 

2,838,669

4.153078768

Sub-Total

     

68,350,955

100

Less Interest Earnings

     

-883,404

 

Total

     

67,467,551

 
           

Proposal #2 Items

         

New Community/Competition Swimming Pool

 

$6,085,327

81.05736009

Synthetic Turf at Sexton and Everett Football Fields

1,422,106

18.94263991

Total

     

7,507,433

100

           

Total Bond

     

75,858,388

 

Less Interest Earnings

     

-883,404

 

Total

     

74,974,984

 
           

Detail

         

Proposal #1 Items 

         
           

New Middle School to Replace Pattengill (including 850 seat performing arts auditorium)

   

Building Construction

     

22,900,500

 

Sitework, Utilities and Athletic Fields

 

2,518,200

 

Furniture & Equipment

     

1,402,390

 

Technology Data Cabling

   

0

 

Site Acquisition Costs

     

0

 

Off Site Utility Improvements

   

500,000

 

Demolish Existing Pattengill

   

500,000

 

Pattengill Site Restoration

   

250,000

 

Sub-Total Construction Costs

   

$28,071,090

 

Project Contingency at approximately 8%

 

2,205,687

 

Total Construction Costs

   

$30,276,777

 

A/E Design and Document Cost at approximately 7%

2,084,374

 

Construction Management

   

535,981

 

Supervision

     

1,004,784

 

General Conditions and Reimburseables at approximately 3.5%

1,042,187

 

Inflation at approximately 3.5%

   

1,042,187

 

Issuance Costs

     

1,057,611

 

Total Project Cost

     

$37,043,901

54.19661071

           
           

Roof, Science & Computer Lab Renovations at Otto Middle School

   

Roof replacement for areas over 20 years old (64,280 sft at $8 per sft)

$514,240

 

Renovate existing science rooms (max. of  7)

 

672,000

 

Renovate existing computer labs (max. of  2)

 

169,000

 

Furniture &  Equipment

     

306,000

 

Sub-Total Construction Costs

   

$1,661,240

 

Project Contingency at approximately 8%

 

132,899

 

Total Construction Costs

     

$1,794,139

 

A/E Design and Document Cost at approximately 7%

125,589

 

Construction Management

   

32,294

 

Supervision

     

146,965

 

General Conditions and Reimburseables at 3.5%

62,794

 

Inflation at 3.5%

     

62,794

 

Issuance Costs

     

76,259

 

Total Project Cost

     

$2,300,834

3.366206076

           
           

Roof, Science & Computer Lab Renovations at Gardner Middle School

   

Roof replacement at all areas over 20 years old

$0

 

Renovate existing science rooms (max. of  7)

 

672,000

 

Renovate existing computer labs (max. of  2)

 

169,000

 

Equipment

     

306,000

 

Sub. Total Construction Costs

   

$1,147,000

 

Project Contingency at approximately 8%

 

91,760

 

Total Construction Costs

   

$1,238,760

 

A/E Design and Document Cost at approximately 7%

86,713

 

Construction Management

   

22,297

 

Supervision

     

146,965

 

General Conditions and Reimburseables at 3.5%

43,356

 

Inflation at 3.5%

     

43,356

 

Issuance Costs

     

42,366

 

Total Project Cost

     

$1,623,813

2.375699067

           
           

Roof, Science & Computer Lab Renovations at Dwight Rich Middle School

   

Roof replacement at all areas over 20 years old

 

$0

 

Renovate existing science rooms (max. of  7)

 

672,000

 

Renovate existing computer labs (max. of  2)

 

169,000

 

Equipment

     

306,000

 

Sub-Total Constructon Costs

   

$1,147,000

 

Project Contingenty at approximately 8%

 

91,760

 

Total Construction Costs

     

$1,238,760

 

A/E Design and Document Cost at approximately 7%

 

86,713

 

Construction Management

     

22,297

 

Supervision

     

146,965

 

General Conditions and Reimburseables at 3.5%

 

43,356

 

Inflation at 3.5%

     

43,356

 

Issuance Costs

     

42,366

 

Total Project Cost

     

$1,623,813

2.375699067

           
           

Renovations at Eastern High School

     

(Eastem football field, track, field lighting and stands to be improved using BTS and Capital Projects Funds - not Bond Issue Proceeds)

   

Roof replacement at all areas over 20 years old (10,820 sft @ $8 per sft)

$86,560

 

Renovate Esisting Science Rooms (max. of 9)

1,080,000

 

Renovate Computer Labs (max. of 2)

 

195,000

 

Furniture and Equipment

   

605,600

 

Weight room and condioning room

   

263,640

 

Locker rooms

     

710,990

 

Renovate Media Center

     

212,400

 

Renovate Gymnasium in Eastern (not the fieldhouse)

830,160

 

Gvmnasium Bleachers

     

0

 

Renovate Cafeteria Eating Area

   

462,500

 

Project Contingency at approximately 8%

 

355,748

 

Total Construction Costs

   

$4,802,598

 
           

A/E Design and Document Cost at approximately 7%

336,181

 

Construction Management

   

86,446

 

Supervision

     

293,930

 

General Conditions and Reimburseables at 3.5%

168,090

 

Inflation at 3.5%

     

168,090

 

Issuance Costs

     

169,465

 

Total Project Cost

     

$6,024,800

8.81450742

           
           

Renovations at Sexton High School

     

Roof replacement at all areas over 20 years old (18,825 sft @ $8 per sft)

$150,500

 

Renovate existing Science Rooms (max. of  9)

1,080,000

 

Renovate Computer labs (max. of  2)

 

195,000

 

Renovate Media Center

     

225,960

 

Renovate Gymnasium

     

708,780

 

Replace Gymnasium Bleachers

   

100,000

 

Replace Concessions Building

   

325,000

 

Renovate Weight Room and Conditioning Room

497,185

 

Locker Rooms

     

543,760

 

Running Track

     

500,000

 

Replace Football Bleachers

   

525,000

 

Replace Footbal Field Lighting

   

140,000

 

Replace Natural Grass Turf &. Drainage

 

250,000

 

Furniture and Equipment

   

608,990

 

Allowance for fields, paving and fencing

 

450,000

 

Renovate Cafeteria Eating Area

   

191,500

 

Sub-Total Construction Costs

   

$6,491,775

 

Project Contingency at approximately 8%

 

519,342

 

Total Construction Costs

   

$7,011,117

 
           

A/E Design and Document Cost at approximately 7%

537,393

 

Construction Management

   

121,340

 

Supervision

     

293,930

 

General Conditions and Reimburseables at approximatey 3.5%

235,939

 

Inflation at approximately 3.5%

   

235,939

 

Issuance Costs

     

223,404

 

Total Project Cost

     

$8,659,062

10.25752603

           
           

Renovations at Everett High School

     

Roof replacement at all areas over 20 years old (18,825 sft @ $8 per sft)

$0

 

Renovate existing Science Rooms (max. of  9)

1,080,000

 

Renovate Computer labs (max. of  2)

 

195,000

 

Renovate Media Center

     

275,220

 

Renovate Gymnasium

     

841,500

 

Replace Gymnasium Bleachers

   

249,625

 

Replace Concessions Building

   

325,000

 

Athletic Site Improvements

   

450,000

 

Furniture and Equipment

   

621,305

 

Renovate Weight Room and Conditioning Room

234,390

 

Renovate Locker Rooms

   

509,040

 

Running Track

     

600,000

 

Replace Football Bleachers

   

50,000

 

Replace Footbal Field Lighting

   

140,000

 

Replace Natural Grass Turf &. Drainage

 

250,000

 

Renovate Cafeteria Eating Area

   

355,250

 

Sub-Total Construction Costs

   

6,176,330

 

Project Contingency at approximately 8%

 

474,106

 

Total Construction Costs

   

$6,650,436

 
           

A/E Design and Document Cost at approximately 7%

482,657

 

Construction Management

   

141,425

 

Supervision

     

293,930

 

General Conditions and Reimburseables at approximately 3.5%

224,015

 

Inflation at approximately 3.5%

   

224,015

 

Issuance Costs

     

219,585

 

Total Project Cost

     

$8,236,063

 
           
           

Magnet School Multipurpose/Cafetorium Addition

   

New Multipurpose Cafetorium (including equipment)

$1,874,844

 

Site Development

     

180,000

 

Sub-Total Construction Costs

   

$2,054,844

 

Project Contingency at approximately 8%

 

158,400

 

Total Construction Costs

   

$2,213,244

 
           

A/E Design and Document Cost at approximately 7%

149,688

 

Construction Management

   

39,838

 

Supervision

     

202,595

 

General Conditions and Reimburseables at approximately 3.5%

77,463

 

Inflation at approximately 3.5%

   

77,463

 

Issuance Costs

     

78,378

 

Total Project Cost

     

$2,838,669

 
           
           
           

Proposal #2 Items (Including professional fees and issuance costs)

   
           

New Community/Competition Swimming Pool

 

$6,085,327

81.05736009

Synthetic Turf at Sexton and Everett Football Fields

1,422,106

18.94263991

Sub-Total

     

$7,507,433

100

           

Note: If proposal #2 passes the $250,000 turf allowance in

   

Proposal #1 at both Sexton and Everett will be used to improve

   

other athletic sites including baseball and softball fields.

   

Source: Lansing School District, 2003